Help to figure out the scheme from TU with the connection of the RKF in the ShR and ShchAO
In specifications, the following schemes are shown as an explanation:
A separate line is shown in the ShchR, the first after the opening machine (AB3): AB4 + RKF
the second line is from the ShchR store (automatic + KM2 + RKF) to ShchAO (+ KM3).
Tell me, please, is the phase monitoring relay common in this circuit? In the diagram in TU they are shown separately in two different groups. But is this possible? I am applying the photo. Thank!
At least that's what I see. Pay attention to the RKF after AB4 is indicated by a square, like a relay coil - this is the conclusion from this. It turns out that the contacts of the RKF include a KM3 coil controlling the operation of emergency lighting (contact KM3 and AB9).
Common in what sense? In this case, the phase control relay is connected to the same phase, it controls the emergency lighting circuit.