How to assemble a 68 kW three-phase switchboard?
Good afternoon! Tell me, from the transformer we carried out SIP4 4 * 50 (connection 380 V, all consumers 220V) and then the question arises, how to organize the connection scheme to the distribution box. shield (introductory, ouzo, automatic machines), if the load is about 68 kW / h
https://our.electricianexp.com/en/instrukciya-po-sborke-trexfaznogo-elektroshhita.html. Install separate machines for lighting and a machine for sockets - this is the minimum, if there is an electric boiler and electric stove - for them on a machine. Connect all groups via RCD. Or use difavtomaty.
Good afternoon! And what's the difference what the total load will be, all the more so NEVER and ANYONE turn on all the equipment at the same time? It is important what your allocated power is. Schemes were considered on the site more than once, at least in this article